Port expansion


In 2017, the Port of Hanstholm turned the first sod to an expansion, including following initiatives:

- New breakwater, better navigation conditions and 11 m depth in the port entry

- East: 135.000 m2 of hinterland with 350 m of quay

- West: 30.000 m2 of multiterminal (function as a port of work in the construction period) with 140 m of quay

- New dock with 10 m depth - and prepared for 11 m

- Breakwater to the west made of concrete (cubipods)

- Breakwater to the east made of quarries (stones)

- Pier head at the western breakwater designed as a caisson

The expansion project will be finished in 2020.

 